What an IFR is

An interim financial report is the unaudited financial report a project submits to its financier during implementation, usually each quarter or each semester. It shows where money came from, what it was spent on against the budget, and the cash position of the designated account. Financiers use it to monitor progress and, on some projects, as the basis for disbursement.

The content, frequency and deadline are set in your financing agreement, disbursement letter or financial management manual. Formats differ between financiers and between projects. Always use the format agreed for your project; the layout below is a typical starting point, not a standard.

The typical report set

  1. Sources and uses of funds. Opening cash, receipts by source, expenditure by category or component, closing cash. For the period, the year to date and the project to date.
  2. Uses of funds by component and activity. Actual expenditure against the budget for the same period, with variances and short explanations.
  3. Designated account statement or reconciliation. Advances received, amounts documented, amounts outstanding, and a reconciliation to the bank statement.
  4. Physical progress. Where required, output or indicator progress linked to the spending, and sometimes a procurement or contract monitoring table.

Typical sources-and-uses layout

LineCurrent periodYear to dateProject to dateBudget (year)
Opening cash balance[amount][amount][amount]—
Receipts: financier advance to designated account[amount][amount][amount][amount]
Receipts: direct payments by financier[amount][amount][amount][amount]
Receipts: counterpart funds[amount][amount][amount][amount]
Total sources[sum][sum][sum][sum]
Uses: Component 1 — [name][amount][amount][amount][amount]
Uses: Component 2 — [name][amount][amount][amount][amount]
Uses: Project management[amount][amount][amount][amount]
Total uses[sum][sum][sum][sum]
Closing cash balance[opening + sources − uses][ ][ ]—

Closing cash must equal the bank balances in the designated and project accounts, after reconciling items. If it does not, the difference needs an explanation before submission.

Problems reviewers flag most often

Before you submit

How projectsmanager.ai builds an IFR

The IFR module builds each line from the records already in the system: work-plan budget lines, recorded expenditure and advances. Every figure opens to the records it was added up from, so a reviewer's question can be answered by clicking, not by searching a spreadsheet.

The output still has to follow the format agreed for your project. Check that it does before you rely on it.

Download the CSV template to start in a spreadsheet.

Open an IFR line to its source

The demo uses fictional data in any country, donor and currency. Click a total and see what it was built from.

Open the demo Request a walkthrough